OpenAI signs a six-year deal with AMD-only cloud startup TensorWave for 457 megawatts of computing power
OpenAI has signed a six-year contract with TensorWave, a Las Vegas startup that rents out computing power built only on AMD chips. The deal covers 457 megawatts of capacity reserved for OpenAI across several US data centers. TensorWave announced it on November 16. Neither company disclosed a price.
The deal is measured in megawatts, the amount of electricity set aside to run the chips, rather than in a number of chips. TensorWave calls it its largest deployment to date.
The deal matters beyond the two companies. In October 2025, OpenAI agreed to deploy 6 gigawatts of AMD's AI chips over several product generations. TensorWave says it is the first specialist cloud provider publicly announced as supporting that agreement. Part of OpenAI's AMD commitment will now come as capacity rented from TensorWave, which, not OpenAI, takes on the job of building out the sites.
What OpenAI is buying
The capacity will run on AMD's newest Instinct MI455X chips, the processors used to train and run AI models. They come packaged in AMD's Helios systems, which ship as a full server rack rather than as individual parts. TensorWave expects the first capacity to come online in the first half of 2027, with full deployment by early 2028. The sites have not been named.
All of this is planned, not built. TechBooky points out that a megawatt figure is a power allocation, not a count of working chips. Delivery still depends on secured sites, grid connections, cooling and installed hardware. TokenPost likewise stresses that the 457 megawatts describes future capacity.
The AMD side of the arrangement gives OpenAI a financial stake in AMD's success. Under the 2025 agreement, AMD granted OpenAI a warrant, a right to buy, for up to 160 million AMD shares. The shares vest in stages as deployments grow toward 6 gigawatts and as AMD's stock hits set price targets. AMD's finance chief said the partnership should bring AMD "tens of billions of dollars in revenue."
AMD's latest results suggest the hardware is starting to flow. Data center revenue rose 97% from a year earlier to $8.5 billion in the third quarter, the company reported on November 3. AMD said OpenAI is among the customers already running work on the first Helios systems. It guided fourth-quarter revenue to about $17 billion.
The building risk sits with a small company
TensorWave's size is the open question for anyone weighing the deal. In June it raised $350 million at a $1.55 billion valuation, in a round co-led by asset manager Magnetar and AMD's venture arm, SiliconANGLE reported. At the time it ran three data centers, in Arizona, Florida and Pennsylvania, of roughly 14 megawatts each. It had signed leases for 500 megawatts, most of which were not yet online.
That means the OpenAI contract alone is more than ten times the power of the three sites TensorWave operated five months ago. The company says it has now lined up more than 2 gigawatts of long-term data center capacity.
Its largest disclosed site shows how much it leans on its chip supplier. In August, TensorWave signed a 15-year, 222-megawatt lease at Fermi America's Project Matador campus in Carson County, Texas. Fermi expects the lease to bring in more than $6.5 billion, Bisnow reported. TensorWave will move in in phases.
Closing on that lease slipped by a month while the parties worked out guarantees, according to Baxtel. AMD then signed a credit support agreement for the first phase, meaning it helps stand behind the obligations. The terms were not disclosed. Neither company has said whether any OpenAI capacity will sit at the Texas site.
The result is a tight loop. AMD helps back the lease of a company whose business is buying AMD chips. That company's new customer, OpenAI, holds a warrant on AMD stock. Chip suppliers backing their own buyers is not unique to AMD. In August, Nvidia agreed to guarantee up to $105 billion for an OpenAI data center campus in Ohio, Fortune reported.
What to watch
First, financing. TensorWave has not said how it will pay for this buildout, and the contract's value is undisclosed.
Second, whether other specialist clouds are named in OpenAI's AMD plan. Fathom News argues more such partners would show the AI buildout can run on more than one chipmaker.
Third, timing. If the first capacity arrives in the first half of 2027 as planned, it will test whether a startup can deliver hundreds of megawatts on schedule. Bisnow reported concerns that Fermi has struggled to secure construction equipment for its campus.
For AMD investors, the deal is evidence that OpenAI's broad commitment is turning into specific orders. For OpenAI, TechBooky notes, it adds a supplier alongside its existing ones rather than replacing them. For TensorWave and its backers, the contract is a large win that now has to be built.