Ohio approves two gas plants that will power data centers without connecting to the public grid
Ohio has approved two of the largest private power plants planned for data centers in the state. The Ohio Power Siting Board, which licenses large generating plants, signed off on both at its Nov. 19 meeting, according to the Columbus Dispatch, Signal Ohio and the Scioto Post.
Together the plants would add 2,150 megawatts of gas-fired generation in central Ohio. That is roughly the capacity of two large nuclear reactors. None of it will reach the public grid. Each plant will be wired straight to the data centers next door, an arrangement the industry calls "behind the meter."
For investors and data center buyers, the approvals matter because they show a growing alternative to waiting for a utility hookup. They also show the new risks that come with it: fuel costs, local opposition and a developer carrying the whole cost of its own power supply.
What was approved
The bigger project is the Fairfield Energy Center in Millersport, east of Columbus. It pairs 1,350 megawatts of gas generation with a 1,040-megawatt battery system on about 122 acres. Its developer is Boston-area Advanced Power, according to Signal Ohio and a local news site, The Reporting Project.
Its only customer will be a four-building campus owned by Vantage Data Centers, a large developer that leases space to cloud companies. Vantage's own project site puts the campus investment at $2.1 billion, with construction running from summer 2026 into early 2030.
The plant's website says it will use up to 40 gas turbines: Siemens units and smaller Titan 130 units made by Caterpillar's Solar Turbines business. Most are mid-size and small units rather than one or two giant utility turbines. As background, the largest turbines have faced order backlogs of several years as data center demand has surged. The developer says the batteries will handle rapid shifts in demand and help the turbines run efficiently.
The second plant is an 800-megawatt facility in Ashville, south of Columbus. It is being developed by PowerConneX, which Signal Ohio identifies as a unit of EdgeConneX, a Virginia-based data center developer. It will feed two EdgeConneX data center buildings.
The board attached 36 conditions to the Millersport plant and 41 to the Ashville plant, the Dispatch reported. They range from emergency plans to construction hours. The Ashville conditions also include payments of millions of dollars toward local parks and public projects. The board noted it has no authority over the data centers themselves, only the power plants.
Why developers are skipping the grid
Ohio's main utility in the Columbus area, AEP Ohio, has made grid power more expensive to commit to. Under a tariff approved by state regulators in July 2025, a large new data center must generally pay for at least 85% of the power it reserves, whether it uses it or not. Contracts run up to 12 years, including a ramp-up period of up to four years.
A private plant avoids those terms and the wait for a grid connection. It also lets developers argue that their growth will not raise household power bills, which has become a sharp political issue. Signal Ohio reported that demand from central Ohio's data center boom has helped push energy prices up.
The catch is that the data center owner now carries the risk a utility would normally spread across millions of customers. If gas prices rise, or a plant has problems, there is no grid connection to fall back on. The Fairfield developer says mobile generators totaling up to about 100 megawatts would supply early power while the main plant is built.
Tax policy is helping close the gap. Signal Ohio reported that recent changes in state law cut property taxes on new power plants. Data centers and the gas plants serving them can also claim sales-tax exemptions on equipment, worth tens to hundreds of millions of dollars over their lives. The Fairfield developer estimates it will pay about $157 million in property taxes over 35 years, a company figure that has not been independently checked.
What could still slow them down
Residents spoke against both plants at public hearings, raising concerns about air pollution, noise and light. At a Nov. 10 Ohio EPA hearing in Millersport, residents said the low-lying area near the water is prone to fog and air conditions that trap pollution near the ground, The Reporting Project wrote. It reported that the Fairfield plant is expected to emit more than 7.2 million tons of greenhouse gases, without saying over what period.
In Ashville, more than 80% of voters this month backed repealing the village's emergency approval of its deal with EdgeConneX, according to Signal Ohio. EdgeConneX told regulators the vote has no effect on the plant or the data center, and construction has continued. How much the vote matters is still unclear.
The approvals are not the last hurdle. Some of the projects still need separate environmental permits for water discharges or backup diesel generators, Signal Ohio reported. Opponents also have 30 days to ask the board to reconsider, The Reporting Project noted. After the board rules on that, they have 60 days to appeal to the Ohio Supreme Court.
That court has already reversed a board approval once this year. In May it sent back an 800-megawatt solar project in Madison County, ruling the board had not done enough on its visual impact. The board reaffirmed that project at the same Nov. 19 meeting.
For buyers of AI computing capacity, the takeaway is practical. Off-grid gas can unlock large sites faster in states where utilities are tightening terms. But it moves fuel, reliability and community risk onto the developer's balance sheet, and those costs are likely to show up in lease prices. Ohio, with at least 195 data centers by one industry count, is now one of the largest live tests of that trade-off.